New Madison Avenue School - Plan

Latest News

Christie Administration Announces the Start of Demolition Activities to Make Way for a New Elementary School in Irvington

Irvington, NJ – The Christie Administration today announced the start of early site preparation activities for the Madison Avenue Elementary School — another significant project being delivered through the efficient and responsible school construction program managed by the New Jersey Schools Development Authority (SDA). The demolition and site preparation activities will make room for a new elementary school to replace the former Madison Avenue Elementary School.
Following completion of demolition and site preparation activities, the SDA will construct a new, approximately 73,000 square-foot, 3-story school facility that will be designed to educate approximately 463 students in grades PK-5. The facility will contain 28 classrooms, a cafeteria, multipurpose room, playground, media center and required administrative spaces. The construction of the new elementary school will reduce overcrowding in the school district. The total estimated SDA project cost for the new school is $35.4 million.
“I am happy to announce that the SDA has advanced preliminary construction work that will prepare the site for the construction of the new Madison Avenue Elementary School,” said SDA CEO Charles McKenna. “We look forward to continuing our collaboration with Dr. Hackett and the Irvington School District as we work to deliver a new school to the Irvington community.”

D&K Construction Company of Middlesex, New Jersey was awarded a $3,043,185 contract to perform demolition and site preparation activities. A Notice to Proceed was issued on April 4, 2016 for phase one work consisting of demolition and removal of all existing above ground and underground structures, removal of unsuitable and/or environmentally impacted soils, and restoration and preparation of the site. SDA will self-manage the early site work. All demolition and associated site work is anticipated for completion in October 2016.
In an effort to utilize practices that have proven successful for the SDA, the new Madison Avenue Elementary School will be constructed using a design-build approach. The design-build method differs from the traditional approach toward bidding projects by allowing the SDA to contract with one firm for both design and construction of school facilities projects. SDA anticipates advertisement of this design-build contract in the third quarter of 2016.

The SDA has invested more than $107 million in completed projects in Irvington alone since the inception of the school construction program, including one new school.

The SDA’s current portfolio of active projects is valued at approximately $2 billion – including the Capital Project portfolios, emergent projects and Regular Operating District grants. SDA currently has 12 school facilities projects in active construction.

Development Timeline

The School Development Authority (SDA) is hopeful that the following information, relating to the Madison Ave Project, will be helpful to you for use as a planning guide. Please be advised, however,  that the dates, activities and other information provided below should be considered tentative as, due to the nature of construction, all are subject to change without notice.

April 13, 2016
The School Development Authority (SDA) is given temporary ownership of the site.

April 20, 2016
Extermination begins

April 25, 2016
Removal of general debris begins

Removal of electronic waste begins

April 29, 2016
Extermination ends

May 3, 2016
Installation of temporary protection, fencing, and signage

Removal of electronic waste begins

May 5, 2016
A community meeting is held at University Elementary School to discuss the project

May 9, 2016
Abatement for asbestos begins (anticipated end date June 10, 2016)

Removal of concrete walkways begins (anticipated end date May 17, 2016)

May 12, 2016
Removal of pavement and contaminated soil begins (anticipated end date May 19, 2016)

Testing of hazardous liquids begins (anticipated end date May 13, 2016)

May 16, 2016
Removal and replacement of chain link fence begins (anticipated end date June 2, 2016)

May 23, 2016
Abatement for asbestos begins (anticipated end date July 15, 2016)

May 27, 2016
Removal of underground fuel lines and sampling begins (anticipated end date June 1, 2016)

June 20, 2016
Removal of remaining pavement and contaminated soil begins (anticipated end date June 27, 2016)

July 18, 2016
Demolition of the building begins (anticipated end date August 26, 2016)

August 22, 2016
Pre-bid meeting and site visit

September 30, 2016
The contractor will begin leveling the ground and installing a permanent fence around the property


October 19, 2016
Closing date for bids

November 9, 2016
Interviews of potential contractors to build the school begins

December 27, 2016
Contract awarded to Ernest Brock & Sons

July 11, 2019
New Madison Avenue School completed